Meeting of the Regional Transport Committee

 

 

Date:                 Tuesday 15 November 2011

Time:                10.15am

Venue:

Council Chamber

Hawke's Bay Regional Council

159 Dalton Street

NAPIER

 

Agenda

 

Item       Subject                                                                                                                  Page

 

1.         Welcome/Notices/Apologies 

2.         Conflict of Interest Declarations

3.         Short Term Replacements for the Regional Transport Committee                                 

4.         Confirmation of Minutes of the Regional Transport Committee held on

            22 September 2011

5.         Matters Arising from Minutes of the  Regional Transport Committee held on 22 September 2011

6.         Action Items from Previous Regional Transport Committee Meetings                         

7.         Consideration of General Business Items

Decision Items

8.         Provisional Adoption of the R Funded Regional Land Transport Programme              

9.         Hastings Model Communities Funding 2012-15                                                            

10.       Additional Meeting in December 2011                                                                           

11.       Regional Representation at National Land Transport Programme (NLTP) Moderation

Information or Performance Monitoring

12.       NZTA Central Region Regional Director's Report                                                         

13.       Verbal Reports from Objective Representatives

14.       RoadSafe Activity                                                                                                          

15.       Public Transport Update                                                                                                 

16.       General Business                                                                                                             

 


HAWKE’S BAY REGIONAL COUNCIL

Regional Transport Committee  

Tuesday 15 November 2011

SUBJECT: Short Term Replacements for the Regional Transport Committee        

 

INTRODUCTION

1.      Council has made allowance in the terms of reference of the Committee for short term replacements to be appointed to the Committee where the usual member/s cannot stand.

 

RECOMMENDATION

1.     That __________________________  be appointed as member/s of the Regional Transport Committee of the Hawke’s Bay Regional Council for the meeting of Tuesday, 15 November 2011 as short term replacements(s) on the Committee for _______________________.

 

 

 

 

 

Helen Codlin

Group Manager Strategic Development

 

   


HAWKE’S BAY REGIONAL COUNCIL

Regional Transport Committee  

Tuesday 15 November 2011

SUBJECT: Action Items from Previous Regional Transport Committee Meetings        

 

INTRODUCTION

1.      Attachment 1 is a list of items raised at previous Regional Transport Committee meetings that require action or follow-up. All action items indicate who is responsible for each action, when it is expected to be completed and a brief status comment. Once the items have been completed and reported to the Committee they will be removed from the list.

 

DECISION MAKING PROCESS

2.      Council is required to make a decision in accordance with Part 6 Sub-Part 1, of the Local Government Act 2002 (the Act). Staff have assessed the requirements contained within this section of the Act in relation to this item and have concluded that as this report is for information only and no decision is required in terms of the Local Government Act’s provisions, the decision making procedures set out in the Act do not apply.

 

RECOMMENDATION

1.      That the Regional Transport Committee receives the report “Action Items from Previous Regional Transport Committee Meetings”.

 

 

 

 

Esther-Amy Bate

Planner

 

Carol Gilbertson

Transport Manager

 

Attachment/s

1View

Action Items from Regional Transport Committee Meetings

 

 

  


Action Items from Regional Transport Committee Meetings

Attachment 1

 

Actions from Regional Transport Committee Meetings

 

The following is a list of items raised at the Regional Transport Committee meetings that require actions or follow-ups. All action items indicate who is responsible for each action, when it is expected to be completed and a brief status comment for each action. Once the items have been completed and reported back to the Committee they will be removed from the list.

 

 

Agenda Item

Action

Person Responsible

Due Date

Status Comment

State Highway 38 – Request for Sealing

To be left on the list for regular follow-ups

 

ongoing

 

Wider Region Transportation Study – M Tonks

Send final report to NZTA for endorsement

CG

Immed

 

Presentation by Mr Martin Matthews CEO, NZTA

Address 18 November meeting

CG/EAB

Progressing

Presentation to be given in February 2012

Presentation on Heretaunga Plains Transportation Study  (GHD Consultants)

Review of Study by Mr Tony Brennan of NZTA

CG

To be completed for presentation at 29 November meeting

Scheduled for 29 November meeting to enable the report to be completed.

Verbal Reports from Objective Representatives

Consideration to erect a BMS sign on the Chesterhope Bridge

GH (NZTA)

Report back to 29 Nov meeting

 

 

 

 

 


HAWKE’S BAY REGIONAL COUNCIL

Regional Transport Committee  

Tuesday 15 November 2011

SUBJECT: Provisional Adoption of the R Funded Regional Land Transport Programme        

 

Reason for Report

1.      The Regional Transport Committee (RTC) is required to prepare a Regional Land Transport Programme (RLTP) for Hawke’s Bay which prioritises all transport projects for funding.

2.      The main focus of this report is the allocation of the regions R funds to projects, as the RTC has been advised that these funds will be the “first port of call” for new and improved transport infrastructure. Prioritised projects included in the RLTP that are not able to funded from R funds are however, still submitted for consideration for funding from N funds.

3.      The regional programme adopted by the RTC has to be forwarded to the New Zealand Transport Agency by 30 November 2011. The NZTA will then consider projects for incorporation within the National Land Transport Programme (NLTP) to be announced next year.

4.      This report sets out the projects recommended by the Technical Advisory Group (TAG) for inclusion into the 2012-15 RLTP against R funds and an explanation for the priority order they have been given

5.      The RTC needs to consider and adopt these recommendations as it considers appropriate.

Statutory Framework

6.      Section 13 of the Land Transport Management Act 2003 requires Regional Councils to prepare and approve a “Regional Land Transport Programme (RLTP)”. Section 13(1) (a) delegates this function to the Regional Transport Committee (RTC).

7.      The preparation of a RLTP is undertaken within the policy framework contained in the Government Policy Statement (GPS) and the Investment and Revenue Strategy. These documents set the national context for prioritising investment in road infrastructure projects across New Zealand. 

8.      The RTC has subsequently requested the TAG to prepare a draft list of projects using R funds for inclusion into the RLTP for the committee to consider.

9.      S16.1(c) sets out the basic steps to be followed when preparing an RLTP. These indicate that all activities or combinations of activities to be included in an RLTP must be prioritised by the promoting region. 

10.    The NZTA’s Planning, Programming and Funding Manual states that the prioritisation processes should adopt the process used by the Agency itself, as the basis for its prioritisation method because:

            “Consistent use of standard methodology will give NZTA confidence that the order of priority is evidence based and will enable the NZTA to use the regional priorities for the purposes of preparing the NLTP”.

11.    The NZTA prioritisation process results in each project obtaining a profile in three categories; Strategic fit, Effectiveness and Economic Efficiency. Each project “scores” a rank of high, medium or low under each assessment category. Projects that score H in one or more categories are more likely to be funded. TAG has followed this approach closely in the preparation of the draft programme.

12.    One factor taken into account by TAG, which is a point of difference and additional to the NZTA methodology, is the reference to and use of the current Regional Land Transport Strategy. The two major studies (the WRTS and HPTS) have also provided significant inputs to the formation of the project list.

13.    These were all used by TAG to help guide the regionalisation of the NZTA methodology (that is putting a Hawke’s Bay focus on the programme).

Background

14.    Over the last three months a series of meetings have been held by TAG. At these meetings TAG has considered a wide range of projects put forward by the Road Control Authorities (RCA) within the region. These projects were all considered for inclusion into and prioritisation within, the new Regional Land Transport Programme.

15.    A list of 27 initial projects was subsequently recommended to and considered by members of the RTC at a workshop held in Hastings. These projects had, for the most part, been identified through previous studies and incorporated into RCA investment programmes (i.e. they had long standing status and acceptance regionally). At the workshop, TAG sought direction from the RTC members on priorities, in order to further refine the list presented.

16.    In response the NZTA representative advised that the list should be refined and targeted more tightly and only incorporate those projects which had sufficiently high profile scores to compete for the limited and available R funding. 

17.    Issues raised by other committee members included the ranking assigned to a number of rated projects – whether these should have a higher or lower priority, the cost of some projects and the need to clearly enunciate the overall strategic direction of the recommendations.

18.    At the RTC meeting held on 22 September 2011, the committee formally confirmed the need for TAG to review the initial list of projects and priorities to ensure that the issues identified at the workshop were properly dealt with. In addition it was advised by NZTA that R funds were to be the first source of funds for all projects in the region whether forwarded as part of the RLTP or applied for directly by road control authorities. 

19.    Consequently, TAG have held further meetings to consider the issues identified by the committee and make adjustments to the proposed programme, in consequence of these. Attachment 1 has resulted from this process and is now recommended for adoption by TAG.

The Process

20.    In undertaking this work TAG has been fully cognisant of the government’s desire to use available R funds to improve productivity and economic efficiency, along with the effectiveness and safety of the countries transport system.

21.    TAG considers that the recommended project list and priorities within it, will fully integrate future and current land use and transport in the region, while “reaping” the best economic, effectiveness and safety returns from the limited R funds available.

 

22.    In reaching these recommendations, TAG has considered:

22.1.         the strategic framework contained within the Regional Land Transport Strategy 2008 (RLTS),

22.2.         the strategic direction (and likely outcomes) of the Heretaunga Plains Transportation Study 2011. This study is based on recent and current development strategies for residential, commercial and industrial activities for the Napier and Hastings urban areas, most notably the Heretaunga Plains Urban Development Strategy 2010 (HPUDS),

22.3.         the strategic issues and recommendations identified in the Wider Region Transportation Study 2011. This looked specifically at HPMV on an intra and inter regional basis; and

22.4.         the project profiles achieved under the NZTA project assessment system for strategic fit, effectiveness and efficiency (BCR)

23.    TAG has also been cognisant of the strategic focus within the region flowing from previous studies (e.g. the HPTS 2004 and Rural Transport Study 2005) and the last RLTP, which all sought to the resolve long term freight transport issues within the region.

24.    Lastly, TAG has taken account of existing strategic development plans of the region’s councils where they relate to and affect the provision of transport infrastructure, particularly in Napier in respect to Prebensen Drive and associated works required along that key freight route to and from the port.

Strategic Focus

25.    Because of the limited funds available to the region, TAG has focussed on the single most important strategic issue facing the region;

“improving the economic efficiency, effectiveness and safety of the routes servicing the regions economic production centres and in particular the transport routes to and from the Port of Napier”.

26.    This has meant that a number of otherwise worthwhile projects have had to be deferred or reduced in scale, in favour of applying the available (limited) R funds to projects that best align with this strategic focus, while at the same time remaining consistent with the criteria which must be applied to satisfy the GPS and IRS and ensure funding is approved by NZTA.

27.    In essence projects have been prioritised to complete key individual elements of the strategic network with the funds available, rather than attempting to address a wider range of problems or every issue raised (even in part).

28.    This was done as it was considered that a broad approach would spread the available funds too thinly and cause the region to miss its primary targets (i.e. achieving the regions aims around freight management, economic development and significant safety issues linked to these projects).

29.    Even so, many projects that are not strategically linked, have been considered and included in the programme for investigation and future implementation as funding becomes available, either through the freeing up of R funds or new N funding,

Risks

30.    The primary risk to the proposed programme arises from the different levels of “certainty” applying to a number of the projects included in the programme.

31.    Some projects are at an advanced stage with all consents obtained and design work largely completed. Others are at a more conceptual stage and there are a number of potential “blocks” to progressing them within the time that the region’s R funds, under the current policy, are likely to remain available.

32.    As such these projects have the potential to “tie up” funds. The worst case scenario arising from this is that the funds are not spent in the region and are reallocated nationally.

33.    TAG therefore considers that contingencies need to be identified to cover the situation where any of the preferred projects, fall behind program and cannot be delivered while R funds remain available.

34.    If this happens and the delivery of a project is not likely to meet the delivery date specified for it (and importantly the use of the regions R funds within Hawke’s Bay), it is recommended that the RTC firstly ask for an extension to the cut-off date for the “commitment of R funds” from Government and failing that being agreed, second, the funds be re-applied at that time to the other high priority projects identified on the list in the RLTP.

35.    A first priority in any reallocation process would be to apply funding to individual projects identified as being “part of” the strategic links contained in the programme.

36.    For instance, in the case of the Whakatu arterial link, this would mean that the intersection upgrade at the Pakowhai Road / expressway junction could proceed as a project or the connection to Pakowhai Road into/out of Whakatu.

37.    As a second priority, other projects in the programme which are ready to proceed (i.e. the next competing project) can be considered. A number of safety focussed projects over and above those already included in the programme would rise closer to the top of the priority list for consideration by the RTC at that time.

38.    With this in mind TAG have prioritised all the potential projects to ensure any reallocation of funds has been properly taken into account and the projects are either consistent with the strategic focus or fully justified under other criteria (e.g. safety) when making a case for funding.

Programme - Strategic projects

39.    The key projects recommended for inclusion into the RLTP, all follow logically on from the strategic approach taken. They reinforce the region’s strong focus on achieving the widest possible range of outcomes (i.e. economic efficiency, effectiveness and safety) but in particular economic development. They all ensure efficient and effective transport links to connect production centres and sources of raw material supplies and enable the export and import of raw materials and finished goods through the port at Napier.

40.    These top projects have in turn been prioritised on the basis of travel from “source to destination” (i.e. hinterland to port), rather than randomly and should all be viewed as strategic works.

41.    They build on the declaration of SH No.2 south as a route of national strategic importance, recent investment in the southern extension of the expressway and the likely significant increased production on the Ruataniwha Plains. All these factors are expected to increase freight flows into and out of Hastings (including Whakatu/Tomoana) for processing and on to the port at Napier for export, in addition to normal economic growth in the region.

42.    This strategic approach has resulted in TAG promoting the following strategic projects (some with a number of major components which can proceed as linked projects or as stand alone projects should the overall link not proceed) for funding through the RLTP.

Origin to expressway

        Whakatu Arterial Link

43.    The first project/priority is the ‘Whakatu Arterial Link’ (including the SH50A / Pakowhai Road intersection, minor upgrades for HPMV and the SH2 / Napier Road intersection). This link connects from Havelock North across to Whakatu and from there across country via the Chesterhope Bridge along Pakowhai Road and onto the expressway towards the Port at Napier.

44.    This link is considered by TAG to be the primary strategic roading infrastructure project in the region and the best fit to the GPS/IRS criteria of increasing economic productivity, effectiveness and safety.

45.    In particular, these works are recommended by TAG because:

45.1.     commercial vehicles (HCV’s and HPMV’s) and production on the Heretaunga Plains, especially through servicing existing industry and its future growth, in the key Whakatu/Tomoana industrial areas, it will provide a more efficient route to the port and more opportunities for HPMV use,

45.2.     it will contribute to significant economic development by enabling improvements in the efficiency of moving export produce from the south and east of Hastings to the port at Napier. It will also enable the movement to/from industrial/cold storage areas at Tomoana and Whakatu of raw materials and finished products,

45.3.     it will alleviate existing and future capacity issues and reduce current transport impacts on residential areas of Hastings by providing an alternative route to reach the expressway, for traffic travelling to the west / north of the Heretaunga Plains and to / from and about the eastern urban area of Hastings / Havelock North. In that respect the TAG considers that this link can be considered to be a partial substitute for the previously proposed Northern Arterial Route (NAR) which ran into land acquisition issues and which was previously the 2nd ranked regional priority work on the Heretaunga Plains; and

45.4.     it will also assist by providing a route to the port for HCV’s which currently choose to travel via the SH No.2 coastal route from out of the region to/from the port at Napier.

46.    While the programme currently indicates an ‘at grade’ solution for the Pakowhai Road / (SH 50A) expressway intersection, this solution is still subject to design investigation. The project scope extends to just north of the Tutaekuri River Bridge, to ensure any proposed solution is future proofed and reflects the expressway’s role as a national strategic highway.

47.    TAG notes that the level of efficiency of any proposed “at grade solution”, needs to be considered against the limited R funding available, the ability to future proof the design and the need to ensure sufficient funds are released and can be applied to other projects, which are value for money and integral parts of the regions strategic approach.

48.    It is also noted that while the Pakowhai Road/(SH 50A) expressway intersection upgrade should proceed for efficiency and safety reasons and as it sits on a national strategic route, regardless of whether the Whakatu arterial link does proceed, as it delivers efficiency and safety benefits to support its implementation in any event.

49.    At present the concepts for the intersection include a “grade separated” and an “at grade” solution. TAG is recommending the adoption of an at-grade solution for inclusion in the programme.

Expressway to destination

       Ford Road Extension

50.    The second project/ priority recommended is the extension of Ford Road (linked projects include Prebensen Drive 4 laning and the Hyderabad Road / Prebensen Drive and Pettigrews roundabout upgrades).

51.    This work is considered to be of strategic importance. It sits on Prebensen Drive, which has been identified as a key route both in terms of accessing the Port of Napier and in servicing the current industrial area of Onekawa and future adjacent Large Format Retail / Technology Park areas.

52.    Because the port and the adjoining industrial/retail areas have such a vital and significant role in the regions economy, and for the port also the national economy, improving the efficiency of this access route, will aide economic development, especially the transport of goods for processing and export, this being fully consistent with the strategic focus adopted.

53.    This work is recommended by TAG because:

53.1.     it improves the utility of Prebensen Drive in its role as the primary connection to the Port of Napier both for traffic originating from sources to the north and west of Napier and from the south,

53.2.     it will enable better control of the Austin Street intersection and so ensure safer and more efficient flows are maintained on Prebensen drive; and

53.3.     by delivering a more efficient link to / from the Onekawa Industrial area onto Prebensen Drive and the wider arterial network and in the process providing for HPMV capability for the Onekawa Industrial area, it ensures more efficient access to / from the port, this creating economic returns at both a regional and national level.

Four Laning of Prebensen Drive

54.    The third project/priority recommended is the 4 laning of Prebensen Drive from the expressway to Hyderabad Road (linked project is the upgrade of Prebensen Drive/ Hyderabad/Pettigrews roundabouts).

55.    This work is considered to be of the same strategic importance as the Ford Road extension. However it needs to follow that work, as the proposed changes at the Austin Street intersection with Prebensen Drive (median separation) that will take place with the 4 laning, require the Ford Road extension to be in place before they can proceed.

56.    As with the Ford Road project, this work will improve the efficiency and effectiveness of Prebensen Drive in its role as a key access to the port at Napier, and in servicing existing and proposed industrial and large format retail areas.

 

57.    This work is recommended by TAG because:

57.1.       it provides for improved east-west connectivity and capacity between the Hawke’s Bay Expressway and the Port of Napier,

57.2.       it will improve traffic flow on Prebenson Drive as the HPTS 2011 has identified a need in the short term to build capacity into the network to accommodate future development adjacent to this route while maintaining efficient access to the port at Napier,

57.3.       it will facilitate HPMV access to the port and the Onekawa industrial area and proposed future industrial (technology park) and large format retail (LFR) development areas,

57.4.       it will enable the better control of access onto Prebensen Drive from adjoining properties/businesses, this enabling route efficiencies, reducing side friction and resulting in road safety benefits; and

57.5.       it will provide improved safety through the provision of off-road cycle and walking facilities alongside the upgraded route consistent with the Napier City Council Walking and Cycling Strategy.

       Prebensen Drive / Hyderabad / Pettigrews Roundabout upgrades

58.    These works should ideally be undertaken at the same time as the 4 laning of Prebensen Drive, funding permitting. It is considered that the existing roundabouts, even with appropriate signage controls, cannot continue to operate effectively in the short to medium term and that the full potential of the 4 lane project would be more likely to be realised with the intersection upgrades.

59.    The unknown factor is how quickly traffic growth rates and local development will affect the level of service at the roundabouts for port related through traffic. The worst case scenarios suggest that in the event that the nearby LFR and industrial areas are developed quickly and the 4 laning is in place, the roundabouts could be under pressure in as little as the next three years.

60.    TAG considers that there may well be other options that should be investigated if pressures do arise even earlier at the roundabouts. Consistent with the overall strategic focus, the installation of a single “slip lane” to provide a direct route from Prebensen Drive towards the port, might still ensure efficient access was available to loaded HCV’s delivering goods to the port for export. However this solution does not deal with all issues identified by NZTA at the roundabouts.

61.    Generally, whatever the upgrade proposal chosen, TAG consider that dealing with the roundabouts is an essential part of the strategic approach taken when preparing these recommendations, as these works will ensure that “local” traffic congestion does not detract from the operational efficiency of the links connecting to the port at Napier.

62.    These works are recommended by TAG because:

62.1.       they will ensure improved connectivity and capacity between the Hawke’s Bay Expressway and the Port of Napier as part of the regions strategic network,

62.2.       they will facilitate HCV and HPMV access to the port, existing industrial areas within Napier and proposed future industrial and retail development areas along Prebensen Drive; and

62.3.       they provide improved links and capacity between the Napier CBD and proposed future commercial and industrial developments along Prebensen Drive.

Programme – Other projects 

63.    TAG notes that all of the following projects can be brought up the programme list at a future date by the RTC, if this is necessary (other projects drop off), desirable (a significant new factor emerges) or possible (additional external funds are released). The RTC is able to adjust the future timing of the construction phase of projects in such situations particularly if national policy or funding is changed, the latter being the most important control factor. As such all the following projects have been placed in an indicative order of priority to enable this to happen with the minimum of delay and seamlessly, should the opportunity arise to do so. Projects which need investigation or design work to be completed to place them in a position to proceed to construction are also included here.

SH No.2 / SH No. 50A Pakipaki intersection

64.    Provision to enable the preparation of a design for this intersection has been made, based on the Committees preference for traffic to be directed to the expressway when heading north across the Heretaunga Plains. While this work has a ranking below the strategic projects, it is recognised that it has strong linkages to these, while also sitting on a national strategic route.

65.    NZTA presently have a commitment to construct passing lanes immediately to the south of this intersection and have advised that they wish to have the opportunity to assess how that project relates to any future changes and design at the intersection.

66.    For these reasons funds for design are provided in the programme, while the construction is ranked so that work can proceed subject to R funding availability. This project is included on the basis that it should proceed, if sufficient R funds remain after the strategic projects have been fully investigated scoped, costed, and committed.

Te Mahanga Passing Lane

67.    Provision for the development of this passing lane has been made, based on high safety benefits, but at a ranking below the strategic projects. This project is included on the basis that it currently has a high benefit/cost ratio (BCR). Because of this, TAG consider that it should proceed, if sufficient R funds remain after the strategic projects have been fully investigated scoped, costed, and committed.

Passing Opportunities SH No.2 north ( at Shaws Cut n/s; Te Ngaru n/s; Waihua n/s)

68.    These projects were part of the previously identified sixteen passing opportunities on State Highway No.2 to the north of the region. They have now been re-profiled. This further analysis was based on the recommendations in the WRTS 2011.

69.    These projects will have the greatest safety and efficiency benefits to road users as the forestry harvest increases over the next 5 years and the number of HCV’s (and possible introduction of HPMV’s) on the route rises. The passing opportunities achieve a BCR above 4.

70.    These passing opportunities are recommended by the TAG for inclusion in the programme, but at a ranking below the strategic projects. These are included on the basis that these projects should proceed, if there are sufficient R funds remaining after the strategic projects have been fully investigated, scoped, costed and committed.

Mahia Access Blacks Beach

71.    Provision of part of the necessary investigation funds is proposed to be made by TAG, to assist Wairoa District Council to assess alternative routes and/or the alternative of a coastal protection structure for the existing route. TAG recognises that WDC can obtain funds through its district roading programme (e.g. maintenance), but given the “lifelines” importance to the Wairoa community of this link, support in the form of “r” funds, even in part, is considered desirable to show regional support. There is also a small risk that future access to emergency funds could be lost, if there is a sudden failure of the route, if this recognition and support is not in place. As such TAG recommends that an allocation of $100,000 investigation funds be included in the RLTP.

SH No.2 / SH No.50 Intersection

72.    A solution for safety issues at the SH No.2/50 intersection has been accommodated in the programme, but at a ranking which sits below the strategic projects. This project is included on the basis that it should proceed, if sufficient R funds remain after the strategic and higher ranked other projects have been fully investigated, scoped, costed and committed.

HB Expressway

73.    The delays currently developing on the HB Expressway north of the Tutaekuri Bridge are proposed to be investigated under the programme. However TAG notes that the extent of available R funds will not be able to cover the cost of dealing with the likely primary cause of these delays on the expressway, these currently being attributed to capacity issues on the two lane Tutaekuri River Bridge.

74.    TAG considers in any event that the proposed programme may relieve an element of the “congestion” with the works proposed around the Pakowhai road / expressway intersection, but at this stage the extent of any relief cannot be determined. The section of the expressway between Kennedy Road, Meeanee and the Tutaekuri River Bridge, has also been identified as having safety issues which will also be investigated under this project.

75.    The solution for these capacity and safety issues has not been identified at this time so provision has been made in the programme for investigations, but at a ranking which sits below the strategic projects.

Regional road safety

76.    The programme already addresses a number of significant safety issues where they occur within the strategic network covered by the main priorities in this programme (e.g. Napier road/SH No 2 intersection). Safety issues which have been identified on other parts of the network are also covered in the programme for investigation, but construction is subject to funding availability.

77.    TAG has agreed to that investigations should however proceed on S.H No 2 between Ellison Street and Awatoto Road because this section of highway is bounded by Norfolk Pines, which pose a known hazard, has been identified in the Kiwirap and has a high profile under the IRS criteria. NZTA has indicated that a number of fatalities and serious accidents on this section of the highway have also occurred over the last 5 years which NZTA attribute to the road / tree configuration.

78.    The safety issue identified by NZTA along the section of SH No.2 between Ellison Street and Awatoto Rd is recommended by TAG to be included in the RLTP for investigation. Any work projects arising from this investigation can be considered for future inclusion in the programme by the RTC, should funds become available after completion of the strategic projects and the other higher ranked projects on the list.

Programme – Conditional projects

Stand Alone Connection at Napier Road / SH No.2

79.    If the Whakatu arterial link does not proceed, TAG recommends that the NZTA proposal to construct a stand alone connection onto SH No.2 at Napier Road, (likely to be a roundabout) proceed for safety reasons. The project is therefore identified in the programme as an independent item, but it is recommended by TAG that it be deferred until the future of the Whakatu arterial link is determined.

Stock Truck Effluent Facility

80.    The provision of a stock truck effluent facility on SH No.2 north of Napier, has been identified in the WRTS as a strategic issue for the region.  The provision of a new facility at Matahoura has been included in the RLTP and prioritised using the default priority rating applied nationally for such facilities by NZTA.

81.    The provision of this facility is dependent upon the Regional Council agreeing to fund the capital cost (other than the roading component which would be undertaken by NZTA) of this project. No such commitment currently exists.

82.    It is however proposed by TAG that funds to complete the design be allocated within the programme, so that in the event that both “surplus” R funds become available within the overall programme and the local share is funded by HBRC, the project is ready to be further considered.

83.    Overall however TAG considers that, because this project has a lower regional priority relative to what the NZTA profiling suggests, makes no strategic contribution to the roading network and there is no commitment to the “local share” of the funding for this work, the construction of this project be deferred at this time.

Programme – long term

Regional network efficiency (Northern, Southern and Western SH links)

84.    The WRTS identified the need for passing opportunities on SH No.2 to the north of the region, but particularly along the section of the route that is anticipated to carry future HCV and HPMV traffic servicing the growing forestry industry. Of the sixteen proposed passing opportunities, three (these are dual n/s configurations) will potentially proceed if R funds become available. However the remaining projects are included at this time on a long term basis.

85.    The nationally strategic route to the south of the region (SH No.2) has been recognised in part, with the recommended inclusion of the Te Mahanga passing lanes subject to funding availability. Additional projects listed for the long term, include Corkscrew Gully, and Silverstream. None of these are however recommended for R funding and are presently recommended by TAG for consideration under N funds only.

Wider Regional Transportation Study

86.    HPMV Capability on SH No.5 between Napier and Taupo is being provided for, as existing structural deficiencies on the two key bridge structures are being managed through NZTA committed works funding. This will result in the bridges being HPMV capable.

87.    The WRTS identifies many other opportunities to develop the regions transport network. These opportunities have been considered by TAG, which recommends that these be followed up, but only as the primary strategy is delivered and/or funds become available.

Heretaunga Plains Transportation Study

88.    Further transportation projects may be recommended at the completion of this study. However, the proposed RLTP, as presented, picks up on the key elements ( major projects) that are likely to be put forward in the finalised document for early completion. These are the Whakatu arterial and linked works and the Prebensen Drive and linked works.

89.    Any other projects will need to be considered by the RCA’s responsible for their delivery and once accepted, will be able to be put forward for consideration in future RLTP.

90.    The most likely of these will be increasing capacity on the expressway, the northern arterial corridor at Hastings (part replacement of the previous NAR) and improving links between Hastings and Havelock North. 

Decision Making Process

91.    As the decision to be made relates to the Draft Regional Land Transport Programme Committee, only the funding organisations can vote on this decision.

92.    The Objective representatives and the representative for cultural interests have full speaking rights however.

93.    Council is required to make every decision in accordance with the provisions of Sections 77, 78, 80, 81 and 82 of the Local Government Act 2002 (the Act). Staff have assessed the requirements contained within these sections of the Act in relation to this item and have concluded the following:

93.1.     Sections 97 and 88 of the Act do not apply.

93.2.     The decisions required will be made under the requirements of the Act.

93.3.     The decision required does not fall within the definition of Council's policy on significance.

93.4.     The persons affected by this decision are road users and the travelling public generally.

93.5.     Assessing options is not required as the Council is carrying out a process required of it by statute.

93.6.     The decision is not inconsistent with an existing policy or plan.

93.7.     Given the nature and significance of the matters to be considered and decided and also the persons likely to be affected by, or have an interest in the decision made, Council can exercise its discretion and make a decision without consulting directly with the community or others having an interest in the decision.

 

Recommendations

That the Regional Transport Committee:

1.       Agrees that the decisions to be made are not significant under the criteria contained in Council’s adopted policy on significance and that Council can exercise its discretion under Sections 79(1)(a) and 82(3) of the Local Government Act 2002 and make decisions on this issue without conferring directly with the community and persons likely to be affected by or to have an interest in the decision due to the nature and significance of the issue to be considered and decided.

2.       Resolves to include within the Regional Land Transport Programme 2012-15 for Hawke’s Bay, the projects and their indicative timing and costing, as set out in this report and as shown in attachment 1 appended to this report subject to:

2.1       any final amendments being made at the meeting, the reasons in paragraphs 19 to 90 of this report being the basis for the programme, and

2.2       the recommended projects being consistent with the recommendations contained in the Heretaunga Plains Transportation Study as adopted at the committee meeting to be held on 29 November 2011.

 

 

 

 

M.J.Buchanan

BESL CONSULTANCY

 

Carol Gilbertson

Transport Manager

 

 Attachment/s

1View

Priority Projects R Funds

 

 

2

Swamp Ramp RLTP NLTP SHP Hawke’s Bay

 

 

  


Priority Projects R Funds

Attachment 1

 

 

 



HAWKE’S BAY REGIONAL COUNCIL

Regional Transport Committee  

Tuesday 15 November 2011

SUBJECT: Hastings Model Communities Funding 2012-15         

 

REASON FOR REPORT

1.      This paper updates the Committee on how the Hastings District Council’s model community projects (iWay) will be funded, summarises the Regional Transport Committee (RTC) position and provides a recommendation from the Chairman of the RTC.

Background

2.      At the meeting of 22 September 2011, NZTA notified the Committee that funding for iWay was to come out of the Hawke’s Bay regional fund allocation (R funds).  The Committee and the region’s council’s had previously understood that funding for iWay would be sourced from the national funds allocation (N funds).   The Committee’s understanding was that as bids for model community projects were contested nationally and they would be funded from a national pool of funds that had been made especially available for this purpose.

3.      The Committee agreed that if R funds were to be used to fund the iWay project it would significantly reduce the regions ability to deliver regionally significant projects as prioritised in the Regional Land Transport Programme (RLTP).  The Committee considered that this would also significantly reduce the strategic benefits of the current RLTP and be to the detriment of the region.  A letter was written to the Minister of Transport on 29 September 2011 by the Chairman of the Committee stating that the Committee was not prepared to accept the use of R funds to fund iWay projects (see attachment 1). 

4.      A letter was received from NZTA on 7 October 2011 stating that the currently committed model community projects would be funded from nationally distributed N funds (see attachment 2).  This included funding approvals relating to iWay projects in the 2010-2011 and 2011-2012 years of the current National Land Transport Programme (NLTP). 

The Way forward

5.      In its letter of 7 October, NZTA stated that while the current iWay projects would be funded out of N funds, future projects will be subject to the NZTA standard funding policy of utilising R funds before N funds.  This policy would apply to any iWay projects in the 2012-2015 RLTP.

6.      The Committee is currently debating project priorities for inclusion into the 2012-2015 RLTP.  If further iWay projects are to be undertaken in the next three years they would have to be funded by R funds as it is not likely that the region will receive N funds for new projects due to the NZTA funding policies and the National Government Policy Statement (GPS) requirements.  A decision must be made at this time on where iWay projects rank against other regionally strategic priorities and whether the Committee is satisfied with funding iWay projects from R funds.

7.      The projects that are currently ranked as high priorities for the region and are to be included into the Draft 2012-2015 RLTP for R funding, have been carefully assessed against the governments GPS and the needs of the region.  The projects, while valuable as stand alone undertakings, are part of an overall package that will give maximum benefits to the community and region as a whole.  The inclusion of iWays projects to the Draft 2012-2015 will reduce the effectiveness and strategic focus of the programme and potential deliver a programme which fails to meet the key GPS focus of economic growth and productivity, value for money and road safety.

8.      The Chairman of the RTC, Councillor Alan Dick, recommends that whist the Committee may wish to support the Hastings iWay project because of its merit, funding for iWay is not sourced from R funds and therefore further iWay projects should not be included in the Draft 2012-2015 RLTP for the above reasons.

DECISION MAKING PROCESS

9.      Council is required to make a decision in accordance with Part 6 Sub-Part 1, of the Local Government Act 2002 (the Act).  Staff have assessed the requirements contained within this section of the Act in relation to this item and have concluded the following:

9.1.   Sections 97 and 98 of the Act do not apply as these relate to decisions that significantly alter the service provision or affect a strategic asset.

9.2.   Sections 83 and 84 covering special consultative procedure do not apply.

9.3.   The decision does not fall within the definition of the Council’s policy on significance.

9.4.   Section 80 of the Act covering decisions that are inconsistent with an existing policy or plan does not apply.

9.5.   Council can exercise its discretion under Section 79(1)(a) and 82(3) of the Act and make a decision on this issue without conferring directly with the community or others having given due consideration to the nature and significance of the issue to be considered and decided, and also the persons likely to be effected by or have an interest in the decisions to be made.

RECOMMENDATIONS

That the Committee:

1.      Agrees that the decisions to be made are not significant under the criteria contained in Council’s adopted policy on significance and that Council can exercise its discretion under Sections 79(1)(a) and 82(3) of the Local Government Act 2002 and make decisions on this issue without conferring directly with the community and persons likely to be affected by or to have an interest in the decision due to the nature and significance of the issue to be considered and decided.

2.      Receives the information in agenda item.

3.      Endorses the Chairman’s recommendation not to fund further iWay projects from R funds and therefore not include further iWay projects into the Draft 2012-2015 RLTP.

 

 

 

Carol Gilbertson

Transport Manager

 

 

Attachment/s

1View

Model Community Funding Attachment 1

 

 

2View

Model Community Funding Attachment 2

 

 

  


Model Community Funding Attachment 1

Attachment 1

 



Model Community Funding Attachment 2

Attachment 2

 


HAWKE’S BAY REGIONAL COUNCIL

Regional Transport Committee  

Tuesday 15 November 2011

SUBJECT: Additional Meeting in December 2011        

 

REASON FOR REPORT

1.      An additional meeting is required in December in order for the Committee to consider and endorse the Regional Land Transport Programme.

General Information

2.      The New Zealand Transport Agency (NZTA) requires that the Regional Land Transport Programme (RLTP) be submitted by 30 November 2011.  Whilst the Territorial Authorities will submit their maintenance and project programmes by 30 November, there will not be time for HBRC staff to compile the overall program for the Committees consideration.

3.      Consequently it is proposed that the Committee meet in December to discuss and formally endorse the RLTP.  Optional dates for this additional meeting are:

3.1.   Thursday 15 December 2011

3.2.   Friday 16 December 2011

3.3.   Monday 19 December 2011

3.4.   Tuesday 20 December 2011

DECISION MAKING PROCESS

Council is required to make a decision in accordance with Part 6 Sub-Part 1, of the Local Government Act 2002 (the Act).  Staff have assessed the requirements contained within this section of the Act in relation to this item and have concluded the following:

3.5.   Sections 97 and 98 of the Act do not apply as these relate to decisions that significantly alter the service provision or affect a strategic asset.

3.6.   Sections 83 and 84 covering special consultative procedure do not apply.

3.7.   The decision does not fall within the definition of the Council’s policy on significance.

3.8.   Section 80 of the Act covering decisions that are inconsistent with an existing policy or plan does not apply.

3.9.   Council can exercise its discretion under Section 79(1)(a) and 82(3) of the Act and make a decision on this issue without conferring directly with the community or others having given due consideration to the nature and significance of the issue to be considered and decided, and also the persons likely to be effected by or have an interest in the decisions to be made.

RECOMMENDATIONS

That the Committee:

1.      Agrees that the decisions to be made are not significant under the criteria contained in Council’s adopted policy on significance and that Council can exercise its discretion under Sections 79(1)(a) and 82(3) of the Local Government Act 2002 and make decisions on this issue without conferring directly with the community and persons likely to be affected by or to have an interest in the decision due to the nature and significance of the issue to be considered and decided.

2.      Agrees to hold an additional Regional Transport Committee meeting in December 2011 to consider and endorse the overall Regional Land Transport Programme.

 

 

 

Esther-Amy Bate

Planner

 

Helen Codlin

Group Manager

Strategic Development

 

Attachment/s

There are no attachments for this report.


HAWKE’S BAY REGIONAL COUNCIL

Regional Transport Committee  

Tuesday 15 November 2011

SUBJECT: Regional Representation at National Land Transport Programme (NLTP) Moderation        

 

REASON FOR REPORT

1.      As part of the National Land Transport Programme planning process, the New Zealand Land Transport Agency receives Regional Land Transport Programmes from around New Zealand then undertakes internal moderation to rank regional projects nationally for funding purposes.  This paper recommends that the Committee seek regional representation at the NZTA internal moderation discussions.

Background

2.      The Regional Transport Committee (RTC) is tasked with compiling the Regional Land Transport Programme (RLTP).  The RLTP contains a list of projects for both the strategic development and the maintenance of the Hawke’s Bay transportation network.  Once approved by the RTC, the RLTP is submitted to the NZTA where it undergoes further assessment and comparison against the National Policy Statement (NPS) and the Investment and Revenue Strategy (IRS).  Hawke’s Bay projects are then assessed against other regions projects and given a national strategic ranking by the NZTA.  This process is undertaken internally by the NZTA to produce the National Land Transport Programme (NLTP) and approve funding for the NLTP period.

3.      At present the moderation discussions for project inclusion into the NLTP is undertaken by the NZTA head office in Wellington with no non-NZTA regional representation.  The Technical Advisory Group (TAG) has discussed the absence of local representation at the NLTP moderation discussions and has agreed to recommend to RTC, that NZTA should be approached to enquire as to whether an individual from the TAG can be included in the NZTA moderation discussions on the Hawke’s Bay section of the NLTP.

4.      TAG considers that the following benefits would be achieved by local representation at the national moderation discussions:

4.1.   It would lend transparency and accountability to the process;

4.2.   A local representative would have the benefit of lending local knowledge and technical advice to the process;

4.3.   The representative would be able to bring back the experience of the process to the RTC and enable the region to be better equipped to design future RLTP’s.

5.      The TAG discussed who would be the best individual to represent the RTC interests in the proceedings and agreed that Mr Murray Buchanan of Buchanan Environmental Services Limited (BESL) has the best mix of technical and planning skills.

DECISION MAKING PROCESS

6.      Council is required to make a decision in accordance with Part 6 Sub-Part 1, of the Local Government Act 2002 (the Act).  Staff have assessed the requirements contained within this section of the Act in relation to this item and have concluded the following:

6.1.   Sections 97 and 98 of the Act do not apply as these relate to decisions that significantly alter the service provision or affect a strategic asset.

6.2.   Sections 83 and 84 covering special consultative procedure do not apply.

6.3.   The decision does not fall within the definition of the Council’s policy on significance.

6.4.   Section 80 of the Act covering decisions that are inconsistent with an existing policy or plan does not apply.

6.5.   Council can exercise its discretion under Section 79(1)(a) and 82(3) of the Act and make a decision on this issue without conferring directly with the community or others having given due consideration to the nature and significance of the issue to be considered and decided, and also the persons likely to be effected by or have an interest in the decisions to be made.

RECOMMENDATIONS

That the Committee:

1.      Agrees that the decisions to be made are not significant under the criteria contained in Council’s adopted policy on significance and that Council can exercise its discretion under Sections 79(1)(a) and 82(3) of the Local Government Act 2002 and make decisions on this issue without conferring directly with the community and persons likely to be affected by or to have an interest in the decision due to the nature and significance of the issue to be considered and decided.

2.      Agrees that the NZTA be requested to include a regional representation in the National Land Transport Programme moderation discussions.

3.      Agrees that Mr Murray Buchanan be put forward as the region’s representative.

 

 

 

Carol Gilbertson

Transport Manager

 

 

Attachment/s

There are no attachments for this report.  


HAWKE’S BAY REGIONAL COUNCIL

Regional Transport Committee  

Tuesday 15 November 2011

SUBJECT: NZTA Central Region Regional Director's Report        

 

Reason for Report

1.      This item introduces the NZTA Central Region Regional Director’s report as provided in Attachment 1.

Decision Making Process

2.      Council is required to make a decision in accordance with Part 6 Sub-Part 1, of the Local Government Act 2002 (the Act).  Staff have assessed the requirements contained within this section of the Act in relation to this item and have concluded that, as this report is for information only and no decision is to be made, the decision making provisions of the Local Government Act 2002 do not apply.

 

Recommendation

1.    That the Regional Transport Committee receives the Regional Director’s report.

 

 

 

 

Carol Gilbertson

Transport Manager

 

 

Attachment/s

1

Regional Director’s Report – Late Item

Under Separate Cover

 


HAWKE’S BAY REGIONAL COUNCIL

Regional Transport Committee  

Tuesday 15 November 2011

SUBJECT: RoadSafe Activity         

 

Reason for Report

1.      This regular report is provided to the Committee to provide a snapshot of relevant road safety activities; and issues that have been actioned since the last Regional Transport Committee (RTC).

Background

2.      Due to the success of the HB Youth Alcohol Expo 2011, planning is currently underway for the 2012 Expo.  A comprehensive Post Event Survey was undertaken, this consisted of 2000 surveys being sent to each of the schools that attended.  The information from this will inform the 2012 event.

3.      With the completion of the DVD, “Just Another Saturday Night”, there has been significant development to support this resource.  This includes the creation of a website, “Jared’s Message”. The website includes information around road safety, events where Jared will be presenting, a question and answer options etc.  Jared’s van has also been sign written promoting the website along with road safety messages. This has proved worthwhile with people approaching him to discuss the website etc

4.      SOBA .D continues to support all RoadSafe HB activities.  We will look to developing further artwork in the future to re-fresh the message.

5.      A story book and CD have been created to promote road safety around child restraints. This is being provided to Early Childhood Centres etc and also to be distributed at Police, RoadSafe HB restraint checkpoints.

6.      Niue: Visual presentation to be provided by Linda Anderson, Regional Manager RoadSafe HB and Snr Constable Iain Cheyne.

Decision Making Process

7.      Council is required to make a decision in accordance with Part 6 Sub-Part 1, of the Local Government Act 2002 (the Act).  Staff have assessed the requirements contained within this section of the Act in relation to this item and have concluded that, as this report is for information only and no decision is to be made, the decision making provisions of the Local Government Act 2002 do not apply.

 

Recommendation

1.    That the RoadSafe Activity Report be received.

 

 

 

Linda Anderson

Regional Manager RoadSafe Hawke's Bay

 

Carol Gilbertson

Transport Manager

 

Attachment/s

There are no attachments for this report.


HAWKE’S BAY REGIONAL COUNCIL

Regional Transport Committee

Tuesday 15 November 2011

SUBJECT: Public Transport Update        

 

Reason for Report

1.      This agenda item provides the Committee with an update on public transport services, including trends since the previous update in July 2011. This report contains patronage and revenue graphs which are updated each month.

General Information

2.      The overall performance of the bus service continues to be positive with good passenger growth and fare recovery levels.

Total Passenger Trips

3.      Since 2009 average monthly trips have trended upward as follows.

2009 – 33,758

2010 – 42,888

2011 (to September) – 51,597

 

The following graph outlines total passenger trips from February 2009 to September 2011.

Diagram 1 – Passenger Numbers – February 2009 - September 2011

Patronage and Financial Trends

4.      The following graph shows a comparison of fare revenue from February 2009 to September 2011.

Diagram 2 – Total Revenue – February 2009 - September 2011

 

Farebox Recovery (total fares as a percentage)

5.      The following graph shows the farebox recovery trend (i.e. the total amount of fares), as a percentage, for each month from September 2010 to September 2011. The average farebox recovery for this period was 38.3%.

Diagram 3 – Farebox Recovery – September 2010 - September 2011

Capacity

6.      This graph shows the seat capacity utilised on a monthly basis from September 2010 to September 2011. The average utilised capacity for this period was 57%.

Diagram 4 – Capacity September 2010 - September 2011


SuperGold Card Trips

7.      The following graph shows the number of SuperGold cardholder trips from September 2010 to September 2011. SuperGold cardholders continue to make very good use of this concession.

Diagram 5 – Number of SuperGold Card Trips – September 2010 - September 2011

Improvements to Bus Services

8.      Increased frequencies on Route 12 services are proving popular with passengers. Services now operate every 15 minutes in peak times and every 30 minutes in off-peak times. Four new buses have been added to the fleet to deliver these services. The increased frequencies make public transport a viable mode of transport for a greater number of people, enabling them to get to and from work on time.

9.      The 6-month trial of a Napier-Ahuriri-Westshore-Ahuriri-Napier service got off to a great start on Monday 17 October. Staff worked closely with Napier City Council to determine the route and bus stop locations for the service. Branded the ‘Hopper’, graphics reflecting the scenic route have been applied to both sides of the bus. Staff have received many phone calls from ratepayers all of a congratulatory/complimentary nature. The trial has been particularly well received by the Ahuriri Business Association, the staff/residents of the Princess Alexander Retirement Village and the Manager of the Crown Hotel. Passenger statistics will be closely monitored and if successful (and approved by Council) this service could become permanent at the end of the trial period.

Infrastructure

Bus Stops

10.    Re-routing all Hastings services through Home HQ (formerly Nelson Park) was due to commence on Monday 31 October. However a recent site visit confirmed that the newly installed speed bumps are not suitable for buses, and HDC are currently working with the developer to find a solution. Once this matter has been resolved and the K-Mart bus stop relocated from Avenue Road to Russell Street (near the Environment Centre), Hastings services will travel along Russell Street, right into St Aubyn Street, left into Holt Place, through Home HQ, right into Alexandra Crescent and right onto Karamu Road.

11.    A new bus shelter was installed at the Lee Road bus stop, near the Meeanee Road intersection in Taradale. The shelter was funded jointly by HBRC and NCC, with NCC taking responsibility for repair and maintenance. Sadly two large glass panels were smashed and had to be repaired within a week of the installation.

Travel Plans

12.    ‘Walk Once a Week’ days are proving to be very successful at St Mary’s School Hastings and Lucknow School Havelock North. Both schools are investigating a ‘kiss’n’drop zone’ to help alleviate congestion and improve safety at the school gate.

13.    The HBRC travel plan team continue to work on initiatives to encourage more staff to use active modes of transport on their journey to and from work, with an emphasis on public transport. Recently staff were offered a goBay smartcard loaded with $40 as an incentive to use public transport. To date 35 staff have taken up this offer and feedback has been very positive, particularly with regard to the improved frequencies/earlier start times on Route 12.

Other

14.    The draft Regional Public Transport Plan (RPTP) was endorsed by the RTC and adopted by Council on 27 July. The RPTP is required to follow Council’s special consultative process under the Local Government Act.

Total Mobility Update

15.    Below is a table showing details of Total Mobility client numbers and expenditure to date for the 2011/12 financial year.

Diagram 6 – Total Mobility Statistics - June to September 2011

Decision Making Process

16.   Council is required to make a decision in accordance with Part 6 Sub-Part 1, of the Local Government Act 2002 (the Act).  Staff have assessed the requirements contained within this section of the Act in relation to this item and have concluded that, as this report is for information only and no decision is to be made, the decision making provisions of the Local Government Act 2002 do not apply.

 

Recommendation

1.      That the Regional Transport Committee  receives the Public Transport Update.

 

 

 

 

Carol Gilbertson

Transport Manager

 

 

Paul Drury

Group Manager Corporate Services

 

Attachment/s

There are no attachments for this report.


HAWKE’S BAY REGIONAL COUNCIL

Regional Transport Committee  

Tuesday 15 November 2011

SUBJECT: General Business        

 

INTRODUCTION

This document has been prepared to assist Committee members note the General Business to be discussed as determined earlier in Agenda Item 6.

Item

Topic

Councillor / Staff

1.   

 

 

2.   

 

 

3.   

 

 

4.   

 

 

5.   

 

 

6.   

 

 

7.   

 

 

8.   

 

 

9.   

 

 

10.