Meeting of the Hawke's Bay Regional Council
Dates: Wednesday 8 June 2016 commencing at 8.30am
and Thursday 9 June 2016 commencing at 9.00am
Venue: |
Council Chamber Hawke's Bay Regional Council 159 Dalton Street NAPIER |
Agenda
Item Subject Page
1. Welcome/Prayer/Apologies/Notices
2. Conflict of Interest Declarations
3. Confirmation of Minutes of the Regional Council Meeting held on 25 May 2016
4. Matters Arising from Minutes of the Regional Council Meeting held on 25 May 2016
Decision Items
5. Remits for LGNZ Annual General Meeting 3
6. Submissions on Our Plan 2016-17 - including Proposed 2015-25 Long Term Plan Amendment and Draft 2016-17 Annual Plan 7
7. Draft Annual Plan 2016-17 Staff Internal Submission 117
Wednesday 08 June 2016
Subject: Remits for LGNZ Annual General Meeting
Reason for Report
1. Hastings District Council is proposing to put forward for consideration to the Local Government New Zealand Conference two remits and is asking for the support of the Hawkes Bay Regional Council in order to obtain approval for these to go forward.
2. The two remits are in respect of:
2.1. Concerns around the decline in community policing and the burden that falls on Councils as a result; and
2.2. Advocacy directed towards central government to establish a fund to support communities to reserve and strengthen publically owned heritage buildings that are earthquake prone.
3. In order for these remits to be put forward the support of five councils is needed. These issues directly affect a wide range of communities and are in accordance with the purpose of local government to meet the current and future needs of communities for good quality local infrastructure, local public services and performance of regulatory functions in a way that is most cost effective for households and businesses.
Details of Proposed Remits
Community Policing
4. Increasing levels of community concern, along with information received about Police restructuring in various areas of New Zealand, indicates that the ‘day to day’ presence of Police in communities throughout New Zealand is shrinking. As well as raising the level of community concerns about community safety, this set of circumstances is placing increasing pressure on Local Authorities to supplement Police services with ratepayer funded security and safety initiatives.
5. Ready access to Police is viewed by communities as a vital contributor to community safety. Community confidence in timely Police response appears to be falling. It is the Government’s role to ensure that Police can respond to community needs and expectations.
6. The remit Council is asked for support calls for LGNZ to advocate to Government for adequate resourcing for Police to ensure community needs can be met, or to fund some of the costs that are falling on councils as a result of insufficient Police resourcing. While overall Police budgets may be gradually increasing over time, this does not appear to be having a positive impact on the resourcing of frontline Policing, particularly in provincial New Zealand. There is acute resourcing pressure on District and Area Commanders to make decisions that provide less that optimal outcomes for communities in terms of access to Police services.
7. This appears to be an issue causing concern for elected members and communities in many councils around the country.
Funding Support for publicly owned heritage buildings that are Earthquake prone
8. The impact of the earthquake prone building regulatory framework is a major issue for local communities across New Zealand and both councils and LGNZ have been involved in the Select Committee legislative process on this matter.
9. The focus of this remit is on how this regulatory framework now impacts on the decisions facing local communities in respect of public heritage buildings which are assessed as earthquake prone. Costs of preservation can be high, and resource constrained councils may make judgements that mean decisions are made not to preserve buildings or that other important infrastructure investment is crowded out by decision to fund heritage preservation.
10. The matter of heritage listed buildings and their protection is a matter of national importance. In many cases these buildings are iconic and represent significant elements of New Zealand’s built and cultural heritage. Their importance crosses territorial authority boundaries as part of the wider New Zealand public good. By their very nature these buildings are expensive to preserve and run the risk of being lost if costs of preservation become too high to be borne locally.
11. While the responsibility of communities to invest in heritage preservation is recognised, the remits is asking for some funding to be made available to lessen the burden on ratepayers.
12. Hastings District Council sees this as a sector wide issue and are recommending that a coordinated advocacy approach is taken by LGNZ on behalf of the sector.
Options
13. There are two basic options available to the Council:
13.1. Option 1 – Endorse the proposed (or as amended) remits for submission.
13.2. Option 2 – not endorse the remits.
14. Option 1 would help enable the remits to be considered at the LGNZ conference to establish how much support they have across the country. This option is recommended. Council would not be bound to support them at the conference, although Hastings District Council would certainly like and appreciate Council’s support.
15. Option 2 would mean that an issue that may be of importance to a number of councils may not get to be debated at conference.
Decision Making Process
16. Council is required to make every decision in accordance with the requirements of the Local Government Act 2002 (the Act). Staff have assessed the requirements in relation to this item and have concluded:
16.1. The decision does not significantly alter the service provision or affect a strategic asset.
16.2. The use of the special consultative procedure is not prescribed by legislation.
16.3. The decision does not fall within the definition of Council’s policy on significance.
16.4. The persons affected by this decision are the ratepayers and residents of the region.
16.5. Options that have been considered include not supporting the remits although this lessens the opportunity for Hastings District Council to submit them for consideration within LGNZ timeframes.
16.6. The decision is not inconsistent with an existing policy or plan.
16.7. Given the nature and significance of the issue to be considered and decided, and also the persons likely to be affected by, or have an interest in the decisions made, Council can exercise its discretion and make a decision without consulting directly with the community or others having an interest in the decision.
That Council: 1. Agrees that the decisions to be made are not significant under the criteria contained in Council’s adopted Significance and Engagement Policy, and that Council can exercise its discretion under Sections 79(1)(a) and 82(3) of the Local Government Act 2002 and make decisions on this issue without conferring directly with the community and persons likely to be affected by or to have an interest in the decision. 2. Supports the remits on Community Policing and Funding for Earthquake Heritage Preservation for Public Buildings being submitted to the Local Government New Zealand 2016 Annual General Meeting. 3. That authority to make changes to the submission to ensure support for the remits be delegated to the Chief Executive in consultation with the Chairman.
|
Liz Lambert Chief Executive |
|
Wednesday 08 June 2016
SUBJECT Submissions on Our Plan 2016-17 - including Proposed 2015-25 Long Term Plan Amendment and Draft 2016-17 Annual Plan
Reason for Report
1. The purpose of this paper is to outline the process to be undertaken to hear and consider submissions received on the proposed 2015-25 Long Term Plan Amendment and draft Annual Plan 2016-17.
Background
2. Our Plan 2016-17 was publicly notified in local media on Saturday 9 April 2016.
3. The availability of the Plan was notified in Hawke’s Bay Today, Central Hawke’s Bay Mail, Napier Mail, Hastings Mail, Wairoa Star, on radio, using social media and HBRC’s website.
4. Four public meetings were held in each of the main centres during May to promote the Long Term Plan Amendment and draft Annual Plan proposals. There was moderate public attendance at meetings: Central HB 13 people, Napier 11, Havelock/ Hastings 11, and Wairoa 20 people.
5. Submissions closed at 5.00pm on Friday 13 May 2016, were acknowledged as having been received and then copies distributed to Councillors on 25 May.
6. This year, Council received 192 submissions in total.
7. Copies of the Staff responses to submissions were sent to each of the submitters on 2 June.
8. In recent years, Council received the following number of submissions in relation to Annual Plan and 10 Year Plan consultations:
8.1. Long Term Plan 2015-25 received 152 submissions
8.2. Annual Plan 2014-15 received 103 submissions
8.3. Annual Plan 2013-14 received 62 submissions
8.4. Long Term Plan 2012-22 received 583 submissions
8.5. Annual Plan 2011-12 received 46 submissions
8.6. Annual Plan 2010-11 received 135 submissions (57 ordinary, 78 s36 charges)
9. The procedure for considering submissions will be that Council:
9.1. Hears all verbal submissions on 8 June as per the attached timetable
9.2. Considers all written and verbal submissions and staff responses to those, as attached, on 9 June
9.3. Considers the Council staff internal submission on 9 June
9.4. Resolves any changes to be made to the 2015-25 Long Term Plan and draft Annual Plan 2016-17 based on the decisions made on submissions from the general public, and Council’s internal submission.
10. Subsequent to Council’s decisions on the submissions, the draft Annual Plan and 2015-25 LTP will be revised to incorporate any necessary amendments. Council will then adopt the final documents on 29 June 2016.
11. Following the adoption on 29 June, each submitter will receive a letter from Council setting out Council's resolution(s) pertinent to their specific submission(s), and the reasons for the resolution(s).
12. The final Annual Plan and LTP documents will be distributed within one month of the date of adoption as required under Section 93 (10) of the Local Government Act 2002.
Decision Making Process
13. Council is required to make every decision in accordance with Part 6 Sub-Part 1, of the Local Government Act 2002 (the Act). Staff have assessed the requirements contained within this section of the Act in relation to this item and have concluded:
13.1. Sections 83 and 85 of the Act set out the requirements of the Act where special consultative procedure applies with consideration of the draft Annual Plan 2014-15.
13.2. The issues to be considered in this paper are those issues raised by members of the community that have submitted to the Council on the Draft Annual Plan. All submissions are an integral part of the special consultative processes set out in Section 83 and 85 of the Local Government Act 2002.
That Council: 1. Agrees that the decisions to be made on issues submitted on “Our Plan 2016-17 - including Proposed 2015-25 Long Term Plan Amendment and Draft 2016-17 Annual Plan” are made after the provisions included in sections 83 and 85 of the Local Government Act 2002 have been followed. 2. Receives and considers the verbal and written submissions. |
Paul Drury Group Manager |
Liz Lambert Chief Executive |
8 June Hearings Timetable |
|
|
|
Proposed 2015-25 Long Term Plan Amendments Submissions Received and Officers' Responses |
|
|
|
Managing & Monitoring Land - Points Raised & Officers' Response |
|
|
|
Fit for Purpose Regional Council - Points Raised and Officers' Response |
|
|
|
Wellington Leasehold Property - Points Raised & Officers' Response |
|
|
|
Rates - Points Raised & Officers' Response |
|
|
|
Business Hawke's Bay & Hawke's Bay Tourism Submissions Received & Officers' Response |
|
|
|
Funding Requests Received and Officers' Responses |
|
|
|
Additional Miscellaneous Submissions Points & Officers' Responses |
|
|
|
Submission Points Relating to Biosecurity, Biodiversity & Land Management Issues & Officers' Responses |
|
|
|
Submission 193 - Owens |
|
|
|
Submission 194 Hawke's Bay A&P Society |
|
Under Separate Cover |
|
Officer's Response to Submission 194 |
|
Under Separate Cover |
Proposed 2015-25 Long Term Plan Amendments Submissions Received and Officers' Responses |
Attachment 2 |
Submission Points Relating to Biosecurity, Biodiversity & Land Management Issues & Officers' Responses |
Attachment 10 |
Submission Points Relating to Biosecurity, Biodiversity & Land Management Issues & Officers' Responses |
Attachment 10 |
Wednesday 08 June 2016
SUBJECT: Draft Annual Plan 2016-17 Staff Internal Submission
Reason for Report
1. This report sets out a number of items that, in the opinion of staff, require inclusion in the Draft Annual Plan 2016/17.
Comments
2. This paper provides the opportunity for Council to consider the following items in relation to the Annual Plan:
2.1. Carry forward of operating expenditure and revenue from 2015/16 to 2016/17.
2.2. Consideration of carry forwards for capital expenditure from 2015/16 to 2016/17.
2.3. Other amendments required to be made to the Draft Annual Plan which reflect changes to proposed Council charges – eg, resource management charges and any substantive changes to wording in other areas of the Annual Plan document.
Carry Forward of Expenditure and Revenue from 2015/16 to 2016/17
Groups of Activities
Strategic Policy
3. Project 192 – Strategy and Planning
3.1. Seek a total of $165,000 to be carried forward from project 192-2380 (consultancy costs). These funds were provided to commission external expert support to the Strategic Development Group’s work programme, particularly in implementing the National Policy Statement for Freshwater Management.
3.2. The primary reason as to why these funds were not spent was due to delays in commissioning, and in some cases completing, contracted work particularly related to the TANK Plan Change. These delays have been driven by staff turnover and vacancies with prolonged processes for successful recruitments, a hiatus in the TANK project through the summer of 2015/16 and delays in the extensive supporting science programme.
Effect on Plan
3.3. An increase in funding for project 192-2380 in 2016/17 funded from unexpended funds in 2015/16.
Recommendation
3.4. That Council approves the carry forward in project 192-2380 of $165,000 from 2015/16 to 2016/17 to cover costs associated with implementing the National Policy Statement for Freshwater Management.
4. Project 192 – Strategy and Planning (Energy Futures)
4.1. Seek a total of $145,000 to be carried forward from Project 192-2385 (contractors). These funds were initially provided in 2014/15 to fund an oil and gas related RRMP plan change, and then in 2015/16 for the development of Energy Futures Strategy for Hawke’s Bay and a plan effectiveness review.
4.2. The primary reason as to why these funds were not spent was due to delays in commissioning work driven by staff turnover and vacancies with prolonged processes for successful recruitments and residual staff effort focussed on other priorities.
4.3. This carry forward request assumes that Council still requires this work to be completed. It should be noted that this project (originally budgeted at $200,000) was funded by a transfer from the Open Spaces and Community Facilities approved borrowing facility.
Effect on plan
4.4. An increase in funding for project 192-2385 in 2016/17 funded from unexpended funds in 2015/16.
Recommendation
4.5. That Council approves the carry forward in project 192-2385 of $145,000 from 2015/16 to 2016/17 to cover costs associated with development and implementation of a HB Energy Strategy, and an oil and gas related plan change should this be required.
5. Project 194 – Response to Climate Change
5.1. Seek a total of $17,000 to be carried forward from project 194-2385 (contractors). These funds were provided to commission external expert advice on issues for climate change adaptation in the HB region.
5.2. The primary reason as to why these funds were not spent was due to delays in commissioning work driven by staff turnover and vacancies with prolonged processes for successful recruitments. The Regional Economic Development Strategy contains a proposed action for the HBRC to identify and proactively manage business risks and opportunities arising from climate change and it is proposed that these funds be applied to undertaking a study with regional partners and central government to give effect to this action.
Effect on plan
5.3. An increase in funding for project 194-2385 in 2016/17 funded from unexpended funds in 2015/16.
Recommendation
5.4. That Council approves the carry forward in project 194-2385 of $17,000 from 2015/16 to 2016/17 to cover costs associated with a study to identify and proactively manage business risks and opportunities arising from climate change.
Regional Resources
6. Project 310 – Regional Groundwater Research
6.1. Seek a total of $231,000 to be carried forward from project 310-2380 (consultancy costs). These funds were originally intended to finance groundwater modelling on the Heretaunga Plains in 2015/16 financial year. The groundwater modelling work programme spans more than one year of effort. Contracts for work have been entered into but the timing of the work is such that the work has been partially undertaken, and will be completed in the next financial year (2016/17).
6.2. $213,000 of the requested sum is to fund work by GNS on the Heretaunga groundwater modelling and the remaining $18,000 to fund work by Jon Williamson and Associates on Heretaunga surface water modelling.
6.3. Section 36 charges associated with project 310 expenses will also need to be carried forward to 2016/17. This equates to 35% of the $231,000 being $80,850.
Effect on plan
6.4. An increase in funding for project 310-2380 in 2016/17 funded from unexpended funds in 2015/16 and a carry forward of associated section 36 income of $80,850 to 2016/17, this is the sum not being charged to consent holders in 2015/16.
Recommendation
6.5. That Council approves the carry forward in project 310-2380 of $231,000 of expenditure from 2015/16 to 2016/17 to cover costs associated with implementing the Heretaunga groundwater modelling and to also carry forward revenue of $80,850 relating to the associated section 36 charges.
7. Project 312 – Regional Surface Water Ecological Research and Investigations
7.1. Seek a total of $40,000 to be carried forward from project 312-2495 (external laboratory testing). The funds are required to complete two elements of this project’s work programme, lake Submerged Plant Indicator (SPI) monitoring, and temperature modelling in the Tukituki catchment, for Plan Change 6 implementation.
7.2. These funds were not spent in 2015/16 because the NIWA lake SPI team was unavailable, and won’t be available until December 2016. In the case of the Tukituki catchment temperature modelling, delay was caused by extended investigation of the best manner in which to implement the work programme. This delay meant the spring and summer window required for monitoring was missed in 2015/16.
7.3. Section 36 charges associated with project 312 expenses will also need to be carried forward to 2016/17. This equates to 35% of the $40,000 being $14,000.
Effect on plan
7.4. An increase in funding for project 312-2495 in 2016/17 funded from unexpended funds in 2015/16 and a carry forward of associated section 36 income of $14,000 to 2016/17, this is the sum not being charged to consent holders in 2015/16.
Recommendation
7.5. That Council approves the carry forward in project 312-2495 of $40,000 of expenditure from 2015/16 to 2016/17 to cover costs associated with undertaking lake SPI and Plan Change 6-related Tukituki temperature modelling and to also carry forward revenue of $14,000 relating to the associated section 36 charges.
8. Project 339 – Regional Land Research and Investigations
8.1. Seek a total of $30,000 to be carried forward from project 339-2380 (consultancy costs). This is to complete wind erosion and riparian work that was not completed during 2015/16 because work in the proposed Heretaunga catchment plan change took priority.
8.2. Section 36 charges associated with project 339 expenses will also need to be carried forward to 2016/17. This equates to 35% of the $30,000 being $10,500.
Effect on plan
8.3. An increase in funding for project 339-2380 in 2016/17 funded from unexpended funds in 2015/16 and a carry forward of associated section 36 income of $10,500 to 2016/17, this is the sum not being charged to consent holders in 2015/16.
Recommendation
8.4. That Council approves the carry forward in project 339-2380 of $30,000 of expenditure from 2015/16 to 2016/17 to cover costs associated with undertaking wind erosion and riparian work and to also carry forward revenue of $10,500 relating to the associated section 36 charges.
9. Project 341 – Air Quality
9.1. Seek a total of $40,000 to be carried forward from project 341-2380 (consultancy costs). $20,000 of this is to complete a contract initiated in April 2016 with GNS for Awatoto Source Apportionment and $20,000 for a review of the Air Quality Monitoring Strategy. The latter project was intended to start when the review by Ministry for the Environment of the NES (Air Quality) had been completed, which is now not likely to be completed until mid-2017.
Effect on plan
9.2. An increase in funding for project 341-2380 in 2016/17 funded from unexpended funds in 2015/16.
Recommendation
9.3. That Council approves the carry forward in project 341-2380 of $40,000 from 2015/16 to 2016/17 to cover costs associated with completing the contract with GNS and for undertaking a review of the Air Quality Monitoring Strategy.
10. Project 380 – Sustainable Land Management
10.1. Seek a total of $100,000 to be carried forward from project 380-2860 (regional landcare grants). These funds were allocated to the early incentivisation of Farm Environmental Management Plans (FEMP’s) in the Tukituki catchment and to support the on-ground works in the Papanui sub-catchment. There is a looming bottle-neck of 1,100 FEMPs being required by landowners by 1 June 2018 with a limited capacity of FEMP providers to meet this demand. The aim of the FEMP incentive is to bring forward as many FEMPs as possible in priority sub-catchments of the Tukituki. The incentive will only run for the 2016/17 financial year after that it is anticipated that landholder demand for FEMP’s will build because of the regulatory deadline. Staff have been working closely with landholders in the Tukituki to promote the early uptake of farm planning, with over 250 landholders in priority sub-catchments being visited since January 2016. Currently 76 landholders are actively working on farm plans this year, of which only 17% of those attending the FEMP workshops had not been visited by staff to promote the scheme.
10.2. The funds will be used to continue subsidising FEMPs for the next 12 months in priority sub-catchments and to support the protection and planting of stream corridor in the Papanui catchment.
Effect on Plan
10.3. An increase in funding for project 380-2860 in 2016/17 funded from unexpended funds in 2015/16.
Recommendation
10.4. That Council approves the carry forward in project 380-2860 of $100,000 of expenditure from 2015/16 to 2016/17 to cover costs associated with incentivising FEMP’s and riparian planting in the Papanui sub-catchment.
Capital Expenditure Adjustments
11. Project 362 – Regional Park Network
11.1. The 2015/25 LTP included a provision of $160,000 per year for the first three years for capital improvements to the Regional Park Network.
11.2. A programme of work for the 2015/16 financial year was approved by Council in August 2015, following consideration by the Environment and Services Committee on 12 August. That programme had an estimated funding requirement of $131,111. The majority of projects outlined in that works programme are expected to be completed by 30 June. Exceptions are:
11.2.1. Pekapeka – land swap and fencing.
11.2.2. Pakowhai – upgrade of gateway signage.
11.2.3. Waitangi – upgrade of gateway signage, pathway to bird viewing hide.
11.2.4. Tutira – upgrade of gateway signage.
11.3. Total expenditure for work expected to be completed by 30 June 2016 is $123,000. Staff seek the remaining $37,000 to be carried forward from the capital provision in project 362-2385 (contractors) to provide for the ongoing programme of capital improvements to the Regional Park network.
Effect on plan
11.4. An increase in funding for project 362-2385 in the 2016/17 year funded from unexpended funds in 2015/16. Council should also note that in December 2015 they approved an increased provision in this project in the 2016/17 year, by bringing forward the $160,000 provision for the 2017/18 financial year, to enable improvement works on Waitangi Regional Park to be undertaken in 2016/17. The capital provision in the 2016/17 year for this work will therefore be $357,000 ($160,000 (2016/17) + $160,000 (2017/18) + $37,000 carry forward).
Recommendation
11.5. That Council approves the carry forward in project 362-2385 of $37,000 from 2015/16 to 2016/17 to cover the costs associated with improvements to the Regional Park Network. Noting that loan funding of $37,000 to fund this capital has been drawn down in the 2015/16 year.
12. Project 913 – Systems Integration Project
12.1. Seek a total of $115,000 to be carried forward from project 913-2380 (consultancy costs). These funds were originally set aside to upgrade our core business platform for Records and Information Management and Process Automation and also to undertake preparatory work (Business Process Mapping) for a Regulatory System Replacement.
12.2. The primary reasons as to why these funds were not spent is set out below:
12.2.1. Upgrade to Core Business Platform (SharePoint 2010) $90,000
· The primary reason as to why these funds were not spent was due to the delay in the release of the replacement platform Microsoft SharePoint 2016 resulted in HBRC having to postpone the upgrade. SharePoint 2016 has now been released to manufacturers and HBRC have gone to market with an RFP seeking a Vendor to perform the upgrade. HBRC expects to select a preferred Vendor no later than Friday 17th June 2016 with an expected upgrade commencing in July/August 2016. Project completion is estimated to be December 2016/January 2017.
12.2.2. Regulatory System Replacement (Business Process Mapping) $25,000
· The primary reason as to why these funds were not spent was due to the delay in availability of key resources and organisational readiness. Initial workshops are expected to commence in July 2016.
Effect on plan
12.3. An increase in funding for project 913-2380 in 2016/17 funded from unexpended funds in 2015/16.
Recommendation
12.4. That Council approves the carry forward in project 913-2380 of $115,000 to cover costs associated with the upgrade of our core business platform for Records and Information Management and Process Automation and also to undertake preparatory work (Business Process Mapping) for a Regulatory System Replacement. Noting that loan funding of $115,000 to fund this capital has been drawn down in the 2015/16 year.
Science Capital
13. Regional Groundwater Research Bores
13.1. Seek a total of $180,000 to be carried forward from the 2015/16 science capital expenditure budget to 2016/17. These funds were originally intended to finance drilling of groundwater monitoring bores as part of Tukituki plan change implementation.
13.2. It has taken some time to establish a suitable contract for drilling services. The work has now been contracted, and commenced in 2016 but it is expected that up to $180,000 of the contract price for drilling may need to be paid early in the 2016/17 financial year rather than the current year.
Effect on plan
13.3. An increase in funding of Science capital expenditure in 2016/17 funded from unexpended funds in 2015/16.
Recommendation
13.4. That Council approves the carry forward of $180,000 from 2015/16 to 2016/17 to cover costs associated with drilling of groundwater monitoring bores for implementing the Tukituki plan. Noting that loan funding of $180,000 to fund this capital has been drawn down in the 2015/16 year.
14. Gauging Structures
14.1. Seek a total of $34,000 to be carried forward from the 2015/16 science capital expenditure budget to 2016/17. These funds were originally intended to finance two science gauging structures.
14.2. Engineers have been unable to produce the required plans that would have enabled our Operations Team to construct the two gauging structures this financial year. They have been working on the plans for some months but after a meeting with all parties involved it was decided there would be insufficient time to fabricate and finish the structures this financial year as intended.
Effect on plan
14.3. An increase in funding of Science capital expenditure in 2016/17 funded from unexpended funds in 2015/16.
Recommendation
14.4. That Council approves the carry forward of $34,000 from 2015/16 to 2016/17 to cover costs associated with two science gauging structures, noting that loan funding of $34,000 to fund this capital has been drawn down in the 2015/16 year.
Building Capital
15. Raffles Street Roofing and Dalton Street Painting
15.1. Seek a total of $30,000 to be carried forward from the 2015/16 building capital expenditure budget to 2016/17. These funds were originally set aside to replace the Raffles Street roof and refresh the Dalton Street stairwells and meeting rooms. The Dalton Street painting has been spread over a longer period to try and reduce disruptions to staff and will be completed in the 2016/17 year. The Raffles Street roof replacement has been delayed to align with the ceiling replacement budget which was set for 2016/17.
Effect on plan
15.2. An increase in funding of building capital expenditure in 2016/17 funded from unexpended funds in 2015/16.
Recommendation
15.3. That Council approves the carry forward of building capital expenditure of $30,000 from 2015/16 to 2016/17 to cover costs associated with the replacement of the Raffles Street roof and general repairs and maintenance for Dalton Street.
Other Amendments Required to the Annual Plan
Resource Management
16. HBRC Charges
16.1. Following consultation late last year with consent holders, Council decided to maintain the status quo by retaining the zone based ‘user – pay’ principle rather than adopting a regional fixed charge. In feedback, consent holders have requested a charging methodology that was simple to understand, equitable and fair, and gave the ability to plan cash flow, by predicting likely charges.
16.2. The proposed additional information to be provided in the plan facilitates this.
16.3. The information relates to the detail on calculating S36 charges and its addition (following legal advice), closes off the potential to appeal these charges as being variable, by fixing them. Fixed charges cannot be appealed. While previous plans have shown at a high level how charges are calculated, the insertion of tables and instruction allows consent holders to calculate likely charges based on the budget for science projects in the zones for the year 2016/17.
16.4. There are no financial impacts other than the benefits of encouraging prompt payment, mitigating the risk of appeal and consequent cost, and providing a positive response to a general request from stakeholders.
Effect on plan
16.5. Greater clarity on annual charges for zone based water science charges for 2016/17.
Recommendation
16.6. That Council approves the inclusion of the tables to calculate Section 36 charges under the HBRC Resource Management Charges section of the Annual Plan, highlighted in pink which is appended as Attachment 1 to this paper.
Summary of Effect of this Submission on the Draft Annual Plan General Funded Surplus/(Deficit)
|
Expenditure
|
Associated Revenue (Loans/Fees/ Reserves etc) |
General Funded Surplus/ (Deficit) |
2016/17 Draft Annual Plan Surplus/(Deficit) |
|
|
$5,000 |
Proposed Carry Forwards |
|
|
|
OPERATING |
|
|
|
Strategy & Planning |
($165,000) |
- |
($165,000) |
Strategy & Planning (Energy Futures) |
($145,000) |
$145,000 |
- |
Response to Climate Change |
($17,000) |
|
($17,000) |
Regional Groundwater Research |
($231,000) |
$80,500 |
($150,500) |
Regional Surface Water Ecological Research & Investigations |
($40,000) |
$14,000 |
($26,000) |
Regional Land Research & Investigation |
($30,000) |
$10,500 |
($19,500) |
Air Quality |
($40,000) |
- |
($40,000) |
Sustainable Land Management |
($100,000) |
- |
($100,000) |
Total Operating |
($768,000) |
$250,000 |
($518,000) |
2016/17 Revised Annual Plan Surplus/(Deficit) |
|
|
($513,000) |
|
Expenditure
|
Associated Revenue (Loans/Fees/Reserves etc) |
General Funded Surplus/ (Deficit) |
Proposed Carry Forwards |
|
|
|
CAPITAL |
|
|
|
Regional Park Network |
($37,000) |
$37,000 |
- |
Systems Integration Projects |
($115,000) |
$115,000 |
- |
Science Capital - Bores |
($180,000) |
$180,000 |
- |
Science Capital – Gauging Structures |
($34,000) |
$34,000 |
- |
Building Capital |
($30,000) |
$30,000 |
- |
Total Capital |
($396,000) |
$396,000 |
- |
Decision Making Process
17. Council is required to make a decision in accordance with the requirements of the Local Government Act 2002 (the Act). Staff have assessed the requirements contained in Part 6 Sub Part 1 of the Act in relation to this item and have concluded the following:
17.1. Consultation on the Draft Annual Plan has been consistent with section 82(a)(3) of the Act which sets out the consultation that is required through the issue of a Consultation Document where there are significant or material differences between the proposed Annual Plan and the content of the LTP for that financial year to which the Annual Plan relates.
That Council: 1. Agrees that the decisions to be made on the issues submitted to the Draft Annual Plan 2016-17 are made after the provisions included in section 82(a)(3) of the Local Government Act 2002 have been followed. 2. Receives and considers Council’s internal submission. |
Manton Collings Corporate Accountant |
Paul Drury Group Manager |
Liz Lambert Chief Executive |
|
2016-17 Annual Plan RMA Charges Amendments |
|
|